Cycle 47r3 has been implemented on the Atos systems in Bologna, starting with today's 06 UTC run
Comment on ATOS vs CRAY forecast differences
Update to option 1 time-critical applications and ECaccess
Update on available test data and products
Atos 47r3 Release Candidate test data available now
47r3 Release Candidate Phase to start on 19 July 2022
Update of implementation timeline
Announcement and availability of test data
Differences in IFS forecasts produced in parallel on CRAY and ATOS systems
Since the ATOS esuite was first introduced the two IFS systems (CRAY and ATOS) have been running independently. Whilst both are fed with the same input data, as the days and weeks pass some minor differences will emerge in the analyses, and therefore in the forecasts (partly linked to the different HPC platforms). Indeed the differences within forecast pairs grow with lead time. These differences are not however indicative of a problem on the ATOS (or the CRAY) but are symptomatic of innate analysis uncertainties. They should be viewed as salutary - highlighting that one cannot rely on deterministic run details, even at short leads. We have also confirmed that statistically the CRAY and ATOS runs are equivalent, with neither better nor worse than the other.
Implementation plan
To switch the operational forecast to the Atos machine we will use a process similar to the implementation of new model cycles. During the Release Candidate Phase we will run a frozen test system in parallel and close to the operational schedule. A Release Candidate Phase of at least 3 months will give forecast users the opportunity to not only test the model output itself but use it to test all other components of the new infrastructure in Bologna. While the model output data on the Atos machine will be different from that currently produced operationally on the Cray, it is expected to be meteorologically equivalent.
Implementation: 06 UTC run on 18 Oct 2022
Indicative timeline
Technical content
Users should not see any technical differences between the Atos IFS Cycle 47r3 data and products and current operational ones produced on our Cray systems in Reading. Users can continue using their existing software packages to decode the Atos IFS Cycle 47r3 data. See 47r3 software requirements for more details.
Atos IFS Cycle 47r3 test data and products
Test data in MARS
IFS Cycle 47r3 Release Candidate test data is available from MARS with experiment version 0077 (MARS keyword EXPVER=0077):
- HRES (class=od, stream=oper, expver=77)
- HRES-WAM (class=od, stream=wave, expver=77)
- ENS (class=od, stream=enfo, expver=77)
- ENS-WAM (class=od, stream=waef, expver=77)
- HRES at 6/18 (class=od, stream=scda, expver=77)
- HRES-WAM at 6/18 (class=od, stream=scwv, expver=77)
- SEAS (class=od, stream=mmsf, expver=9001, from August)
Only users registered with access to MARS will be able to access these test data sets. The data should not be used for operational forecasting. Please report any problems you find with this data via the ECMWF Support Portal.
The Release Candidate test data in ECPDS, available from , will be generated daily, shortly behind operational high resolution and ensemble runs and based on the operational dissemination requirements. The availability of the test data does not follow any strict schedule.
For longer time series available beta test data with EXPVER=9077 from can be used. For access to CAMS data please see Accessing CAMS 47r3 technical test data
Test data in dissemination
Cycle 47r3 test data from the Release Candidate Phase will be available through the test dissemination system, starting from the 00Z run on . Users with access to ECPDS can login to the test system in Bologna at https://xdiss-monitor.ecmwf.int/do/start and trigger the transmission of test products in the usual manner (for ECPDS access to CAMS please see Accessing CAMS 47r3 technical test data). To receive the test data from Bologna, we will remind users to have their firewall open to the relevant ECPDS Data Movers (cf. https://confluence.ecmwf.int/x/FyFEDg):
Internet:
- 136.156.192.0/26
- 136.156.193.0/26
RMDCN:
- 136.156.196.0/26
- 136.156.197.0/26
The Atos IFS Cycle 47r3 test products are available as version number 77 (file names ending with '77' with the ecCodes key expver=77 in the GRIB messages) and are intended to be generated shortly behind real-time. The test products will be based on the operational dissemination requirements and updated in near real time when changes to the requirements are made. The test products will be available for HRES, HRES-WAM, ENS, ENS-WAM, ENS extended and SEAS. Test data from the Boundary Condition program, HRES and ENS runs at 06:00 and 18:00 UTC, is also available.
Access to the operational PREd will be closed at 9 UTC on 16 October. Any changes to the operational requirements can be implemented after 10 UTC on 18 October.
If you don't have access to the ECPDS system or PREd or should you require any assistance with Atos IFS Cycle 47r3 test dissemination products, please contact us via the Support Portal.
Dissemination hosts on test ECPDS
The ECPDS dissemination hosts on the test dissemination system in Bologna have been copied over from the operational ECPDS system in Reading. Unlike the PREd requirements, the destination hosts in Bologna will not be automatically updated during the Release Candidate Phase, unless agreed with our users. Please do contact us via the Support Portal if any destination hosts need to be updated under ECPDS in Bologna.
Migration of data dissemination
ECMWF will also contact very shortly our users with access to ECPDS to offer further options to test the ECPDS from Bologna. See Migration of data dissemination (ECPDS).
ECPDS through ECaccess now available
ECaccess is now available in Bologna. Remote sites are advised to install the the latest gateway package to be able to connect to the ECMWF gateway based in Bologna, boaccess.ecmwf.int, via the Internet. For any issues please contact us via the Support Portal.
Graphical display of test data in ecCharts
For this technical change it is not planned to make IFS cycle 47r3 Release Candidate test data available in ecCharts.
Web charts based on test data
For this technical change it is not planned to make available OpenCharts based on the Atos IFS cycle 47r3 Release Candidate test data.
WMO Essential and Additional test data
IFS cycle 47r3 WMO Essential test data starting from the 00Z run on is available at https://xdiss.ecmwf.int/ecpds/home/wmo/.
Time-critical applications
Option 1 - simple time-critical jobs
Member State users of the "Simple time-critical jobs" framework can test that their scripts/jobs will work with the IFS Cycle 47r3 test data on the Atos by using the limited ECaccess 'events' set up for this purpose.
1633 | e_ms090 | At this stage, the e-suite step 090 (HRES-BC) has been generated. |
1634 | e_ms144 | At this stage, the e-suite step 144 (ENS-BC) has been generated. |
1635 | e_ms240 | At this stage, the e-suite step 240 (HRES) has been generated. |
1636 | e_ms360 | At this stage, the e-suite step 360 (ENS) has been generated. |
1638 | e_ms1104 | At this stage, the e-suite step 1104 (ENS extended) has been generated. |
1639 | e_msrefc | At this stage, the e-suite step refc (REFORECAST) has been updated. |
For these events, MSJ_EXPVER environment variable is set to 0077 and can be used to specify the IFS Cycle 47r3 test data in any MARS retrievals. These events are intended for testing technical aspects only and should not be used for operational time-critical activities. Please note that ECaccess events for the operational production (expver=1) are also available, both in Reading and Bologna.
For data transfers using ectrans remote sites are advised to upgrade their ECaccess gateways with the latest gateway package to be able to connect to the ECMWF gateway based in Bologna, boaccess.ecmwf.int, via the Internet.
Options 2 and 3
Option 2 or 3 time-critical applications can be tested with the Atos IFS Cycle 47r3 test data retrieved from MARS or received in Dissemination.
ECPDS Destination hosts in Bologna for Option 2 activities